13.11.2019

Our new theatre building for Horris Hill School, Newbury, now has half the foundations poured and with the slab completing this week we are expecting delivery from Austria of the Cross Laminated Timber walls and roof in 10 days. Once the timber is on site the superstructure should be erected in under 5 weeks, leaving us wind and water tight for the Christmas period. The chamfered concrete profile is a bench facing the school playing fields and will provide the backdrop to an outdoor amphitheatre for summer performances.