25.10.2016

This week the JTD office paid a visit to our project on the Hackney Road to catch up with the progress on site.

Six months into the construction phase, the timber frame is complete and currently being insulated with wall linings to follow. The polished concrete floor has been poured and all the first fix M&E is now installed. Window openings are complete and temporarily sealed; the building will soon be weather tight for the winter.